← Hickory Data Centre — Truganina
Custom in-ground post — Hickory DC east and south
High Coating
Sell value$74,160ex GST
Cost to make$44,823material, labour and coating
Gross profit$29,33739.6% margin
Hours88.0of 104 estimated
Operation card
6 of 8 complete Cut Bandsaw & Cutting 713 min 9 Aug, 10:00am
Owen Fitzgerald
Owen Fitzgerald
Bend Press & Folding 933 min 11 Aug, 10:00am
Owen Fitzgerald
Owen Fitzgerald
Fabricate Fabrication Bay 1 723 min 13 Aug, 9:00am
Owen Fitzgerald
Owen Fitzgerald
Weld Welding Bay 777 min 15 Aug, 9:00am
Owen Fitzgerald
Owen Fitzgerald
Blast Blast Booth 851 min 17 Aug, 1:00pm
Owen Fitzgerald
Owen Fitzgerald
Coat Powder Coating — Batch Plant 897 min 19 Aug, 1:00pm
Owen Fitzgerald
Owen Fitzgerald
QA QA & Packing 780 min est Running
Pack QA & Packing 780 min est Waiting
Materials
$82,571 at cost| Item code | Description | Required | Issued | In stock |
|---|---|---|---|---|
| POST-100-42 | Fence Post 100NB x 4.2m — HDG | 397 ea | 397 | 2 |
| HDG-100-45-M | 100 NB x 4.5mm HDG Pipe — Grade M | 180 length | 180 | 328 |
| HW-BOLT-M12 | Cup Head Bolt M12 x 40 — HDG | 468 ea | 468 | 67 |
Details
- Customer
- Hickory Group
- Project
- Hickory Data Centre — Truganina
- From quote
- Q-2026-0450
- Type
- Posts
- Quantity
- 180 ea
- Work centre
- Fabrication Bay 2
- Assigned
- Owen Fitzgerald
- Opened
- 6 Aug 2026
- Due
- 21 Aug 2026
- Colour
- Monument®
- Powder
- Dulux · Satin
- Drawing
- DG-4412-P2
Move stage
Moving to Blast or Coating books this job into the coating queue with its m² and colour already on it.
In the booth
| CD-2026-0910 Powder coat only | 378.0 m² | In coating run |
Specification
1km of 3.6m 358 security mesh, 500m custom base-plated and in-ground posts, HDG then powder coat to Monument. Doogood warranty coating system.
Edit job
Log hours against this job