← Hickory Data Centre — Truganina
Replacement post — Hickory DC, 6 damaged in transit
Scheduled
Sell value$18,353ex GST
Cost to make$9,727material, labour and coating
Gross profit$8,62647.0% margin
Hours0.0of 8 estimated
Operation card
0 of 8 complete Cut Bandsaw & Cutting 60 min est Waiting
Bend Press & Folding 60 min est Waiting
Fabricate Fabrication Bay 1 60 min est Waiting
Weld Welding Bay 60 min est Waiting
Blast Blast Booth 60 min est Waiting
Coat Powder Coating — Batch Plant 60 min est Waiting
QA QA & Packing 60 min est Waiting
Pack QA & Packing 60 min est Waiting
Materials
$4,374 at cost| Item code | Description | Required | Issued | In stock |
|---|---|---|---|---|
| POST-100-42 | Fence Post 100NB x 4.2m — HDG | 13 ea | 0 | 2 |
| HDG-100-45-M | 100 NB x 4.5mm HDG Pipe — Grade M | 14 length | 0 | 328 |
| HW-BOLT-M12 | Cup Head Bolt M12 x 40 — HDG | 5 ea | 0 | 67 |
Details
- Customer
- Hickory Group
- Project
- Hickory Data Centre — Truganina
- From quote
- Q-2026-0450
- Type
- Posts
- Quantity
- 6 ea
- Work centre
- Fabrication Bay 1
- Assigned
- Owen Fitzgerald
- Opened
- 26 Jul 2026
- Due
- 24 Aug 2026
- Colour
- Monument®
- Powder
- Dulux · Satin
- Drawing
- DG-4412-P3
Move stage
Moving to Blast or Coating books this job into the coating queue with its m² and colour already on it.
Specification
1km of 3.6m 358 security mesh, 500m custom base-plated and in-ground posts, HDG then powder coat to Monument. Doogood warranty coating system.
Edit job
Log hours against this job