← NEXTDC M3 — Port Melbourne Stage 2
Sliding gate 7.2m — NEXTDC M3 loading dock
High QA
Sell value$39,600ex GST
Cost to make$26,646material, labour and coating
Gross profit$12,95432.7% margin
Hours76.5of 74 estimated
Operation card
7 of 8 complete Cut Bandsaw & Cutting 536 min 24 Jul, 10:00am
Adem Yilmaz
Adem Yilmaz
Bend Press & Folding 599 min 26 Jul, 10:00am
Adem Yilmaz
Adem Yilmaz
Fabricate Fabrication Bay 1 573 min 28 Jul, 3:00pm
Adem Yilmaz
Adem Yilmaz
Weld Welding Bay 568 min 30 Jul, 12:00pm
Adem Yilmaz
Adem Yilmaz
Blast Blast Booth 674 min 1 Aug, 9:00am
Adem Yilmaz
Adem Yilmaz
Coat Powder Coating — Batch Plant 529 min 3 Aug, 9:00am
Adem Yilmaz
Adem Yilmaz
QA QA & Packing 594 min 5 Aug, 9:00am
Adem Yilmaz
Adem Yilmaz
Pack QA & Packing 555 min est Running
Materials
$267 at cost| Item code | Description | Required | Issued | In stock |
|---|---|---|---|---|
| HDG-50-36-M | 50 NB x 3.6mm HDG Pipe — Grade M | 3 length | 3 | 40 |
| HW-BOLT-M12 | Cup Head Bolt M12 x 40 — HDG | 1 ea | 1 | 67 |
| FIT-GUD-16 | Gudgeon Hinge 16mm — HDG | 2 ea | 2 | 105 |
Details
- Customer
- NEXTDC Limited
- Project
- NEXTDC M3 — Port Melbourne Stage 2
- From quote
- Q-2026-0457
- Type
- Gate
- Quantity
- 2 ea
- Work centre
- Welding Bay
- Assigned
- Adem Yilmaz
- Opened
- 21 Jul 2026
- Due
- 19 Aug 2026
- Colour
- Night Sky®
- Powder
- Dulux · Gloss
- Drawing
- DG-4488-G1
Move stage
Moving to Blast or Coating books this job into the coating queue with its m² and colour already on it.
Specification
3.0m 358 mesh perimeter with DooMAX VRF to the substation compound. Anti-climb, concealed fixings, Night Sky.
Edit job
Log hours against this job