J-2026-1416 Trackside gate 3.6m — Noble Park crossover
MYOB · connected 16 Aug 2026
← Dandenong Corridor — Level Crossing Removal

Trackside gate 3.6m — Noble Park crossover

J-2026-1416 · Gate · 4 ea · Metro Trains Melbourne · DG-4444-G1
Critical Fabrication
4 days past due
Promised 12 Aug 2026. Running 14.0 hours over estimate.
Sell value$9,734ex GST
Cost to make$13,991material, labour and coating
Gross profit-$4,257-43.7% margin
Hours96.0of 82 estimated

Operation card

3 of 8 complete
Cut Bandsaw & Cutting 563 min 14 Jul, 3:00pm
Tony Milenkovic
Bend Press & Folding 730 min 16 Jul, 3:00pm
Tony Milenkovic
Fabricate Fabrication Bay 1 675 min 18 Jul, 9:00am
Tony Milenkovic
Weld Welding Bay 615 min est Running
Blast Blast Booth 615 min est Waiting
Coat Powder Coating — Batch Plant 615 min est Waiting
QA QA & Packing 615 min est Waiting
Pack QA & Packing 615 min est Waiting

Materials

$366 at cost
Item codeDescriptionRequiredIssuedIn stock
HDG-50-36-M 50 NB x 3.6mm HDG Pipe — Grade M 4 length 4 40
HW-BOLT-M12 Cup Head Bolt M12 x 40 — HDG 5 ea 5 67
FIT-GUD-16 Gudgeon Hinge 16mm — HDG 4 ea 4 105

Details

Customer
Metro Trains Melbourne
Project
Dandenong Corridor — Level Crossing Removal
From quote
Q-2026-0471
Type
Gate
Quantity
4 ea
Work centre
Fabrication Bay 1
Assigned
Tony Milenkovic
Opened
11 Jul 2026
Due
12 Aug 2026
Colour
Ironstone®
Powder
Dulux · Satin
Drawing
DG-4444-G1

Move stage

Moving to Blast or Coating books this job into the coating queue with its m² and colour already on it.

Specification

Trackside 358 mesh 2.4m with tension wire top, 6.2km. Rail-corridor coating spec, Ironstone.