DDoogood
DDoogood Australia
CD-2026-0919 Ball-stop extension frame 6.0m — Casey Fields — internal, from J-2026-1299
MYOB · connected 16 Aug 2026
← Coating Intake

Ball-stop extension frame 6.0m — Casey Fields — internal, from J-2026-1299

CD-2026-0919 · City of Casey · Gates · Received 15 Aug 2026 · Doogood's own job
Blasting
Surface area938.4 m²138 ea · 16,891 kg
TreatmentBlast + powder coatAS1627.4 Class 2.5 · AS4506-2005
Colour Cottage Green® Dulux Duratec · Satin
Cost centre Job charged to J-2026-1299

Progress through the plant

Booked in Done
Received Done
Blasting Now
Ready to coat
In coating run
Curing
QA
Ready for despatch
Despatched

Details

Customer
City of Casey
Project
PRJ-2026-019
From job
J-2026-1299
Received
15 Aug 2026
Promised
23 Aug 2026
Treatment
Blast + powder coat
Colour
Cottage Green®
Powder
Dulux Duratec
Gloss
Satin
Surface
938.4 m²
Linear
2,252 m
Weight
16,891 kg
Longest piece
6.0 m
Booked in by
Luke Antoniou

Move status